Framing Week 18 and Windows

 

The crew got 3 days of work in this week.  It was so windy on Wednesday that they were not able to work safely since their main jobs included roofing and windows.

In the 3 days, they were able to finish shingling the roof of the main portion of the house, as well as the kick out roof over the dining room.  They also completed the sheathing on the garage, shingled one side of the garage, and set the final roof ridge for the roof over the mudroom and laundry room.  This is the last portion of the roof that needs to be completed on the house.

The windows were delivered this week, and the crew began installing them.  They were able to able to get about 80% of them in.  We also have the front door and french doors for the great room, but we are waiting to install the front door for a little bit to keep it from getting damaged.

The following pictures are from the week of March 23-29, 2014.

 

a3.25.14-1

a3.25.14-2

a3.27.14-4

a3.27.14-10

a3.28.14-1

a3.28.14-2

a3.28.14-3

a3.27.14-7

a3.27.14-8

a3.27.14-9

a3.27.14-1

a3.27.14-2

a3.27.14-3

a3.27.14-6

 

Leave a comment